Name Of The Project Construction of Major Bridge No.63 (Open web girder) & No. 66 (PSC slab) with pile foundation & RCC substructure, Earthwork, Blanketing, Mechanical compaction etc. in approaches and other allied works in connection with Doubling of Delang-Puri Section of KUR Division in between Km.482.40 to Km. 499.180
Client East Coast Railway, Bhubaneswar-23
Project Location Orissa
Project Value 1,432 Lakhs
Period of Completion 19 Months
Year of Completion 2015
Salient Features/Work Description Major Bridge of length 198m with individual Spans 61.0m & 45.7 m of Steel Girders on Pile Foundation with RCC Superstructure, Earthwork, Blanketing, Mechanical compaction etc. in approaches and other allied works
Name Of The Project Improvement of Movement Network in Nanded City under JNNURM.
Client Nanded Waghala City Municipal Corporation, Nanded
Project Location On The Godavari river
Project Value 6,023 Lakhs
Period of Completion 55 Months
Year of Completion 2012
Salient Features/Work Description Four lane Bridge of length 859 m with approaches, the span of ridge is 32m of 19 spans with piling as foundation
Name Of The Project Improvement & Widening of Jalandhar - Amritsar (BOT) Road Project, from km 407.100 to km 456.100 of section of NH-1 in state of Punjab.
Client IVRCL Infrastructures & Projects Limited, Hyderabad
Project Location Punjab
Project Value 3,709 Lakhs
Period of Completion 34 Months
Year of Completion 2010
Salient Features/Work Description Major Bridge at Km.412.218 (Bridge No.413/1) Across River Beas.
Name Of The Project Execution of balance work of foundation, substructure and construction of superstructure of major bridge no.382(10x30.50m span PSC Girder at Km.148.683 in connection with Tomka Baspani Rail Link Project.
Client East Coast Railway, Bhubaneswar-23
Project Location Orissa
Project Value (Rs. In Lakhs) 1,209 Lakhs
Period of Completion 27 Months
Year of Completion 2006
Salient Features/Work Description Bridge Foundation & Superstructure of 10 x 30.5m span